Bengaluru tunnel road to bypass Lalbagh; survey underway for alternative routes, says Minister Krishna Byre Gowda

The government is also negotiating with the contractor to bring down the project cost, he said. Adani Enterprises emerged as the lowest bidder for two packages of the project, with a bid of ₹22,000 crore.

Published Nov 25, 2026 | 7:11 PM ⚊ Updated Nov 25, 2026 | 7:11 PM

Bengaluru tunnel road to bypass Lalbagh; survey underway for alternative routes, says Minister Krishna Byre Gowda
Make Us Your Preferred Source on Google

Synopsis: Karnataka Minister for Greater Bengaluru Development Krishna Byre Gowda on Wednesday said the alignment of the proposed Bengaluru tunnel road would be changed to take it outside Lalbagh following opposition from citizens, Opposition parties and environmentalists. The government has begun a survey and shortlisted two alternative locations, while a committee is negotiating with the contractor to reduce the project cost.

Karnataka Minister for Greater Bengaluru Development Krishna Byre Gowda on Wednesday, 25 November, said the alignment of the proposed Bengaluru tunnel road would be changed to take it outside Lalbagh, following fierce opposition to the project from citizens, Opposition parties and environmentalists. The government has begun a survey to identify an alternative route and has shortlisted two locations.

Advertisement
Advertisement

“The alignment will definitely be changed, so there is no need for any confusion about that. Correct, the alignment will be changed. We have given the people a promise through the Hon’ble Chief Minister that we will move it outside Lalbagh. We are committed to that promise,” Gowda said, speaking to the media.

The project, initiated by Chief Minister DK Shivakumar soon after the Congress returned to power in 2023, proposes a tunnel road connecting Hebbal in north Bengaluru with Silk Board in the south-east. Mobility experts have described it as a stopgap solution to the city’s traffic congestion.

The government is also negotiating with the contractor to bring down the project cost, he said. The Cabinet has constituted a committee headed by the Chief Secretary, with representatives from the Finance Department, the Public Works Department and other departments, to negotiate the rates.

The committee has already held one or two rounds of talks with the contractor.

“Efforts are underway to reduce the rates. The survey is also underway. We have identified one or two alternative locations, considering their pros and cons, and we will finalise the location as well,” the minister said.

Also Read: ‘Unviable, unscientific’: BJP MP Tejasvi Surya blasts controversial Bengaluru tunnel road project

Fierce opposition from citizens, environmentalists

The original alignment came under particular scrutiny because it passes beneath Lalbagh, one of Bengaluru’s last remaining green spaces.

The Geological Investigation Report (GIR), prepared for the Bruhat Bengaluru Mahanagara Palike by Rodic Consultants and published in September 2024, identifies the Lalbagh stretch as a bedrock transition zone. It also records a prominent lineament, a linear geological feature that can indicate a fault or fissure, crossing the proposed tunnel alignment near Lalbagh Lake.

The Detailed Project Report (DPR) proposes two three-lane tunnels, each with a 10.5-metre-wide carriageway comprising three 3.5-metre lanes and a finished diameter of 13.5 metres.

At Lalbagh, the DPR provides for a 320-metre cut-and-cover section on the entry ramp and a 60-metre section on the exit ramp. Both are designed as two-lane structures.

Gowda said the government would consult stakeholders before choosing an alternative, as every possible location came with its own set of issues. “We are in that process. We have identified one or two alternatives, and we will finalise one of the two as soon as possible. I will inform you once it is finalised,” he said.

The revised alignment will have to go back to the Cabinet for approval before the government issues a work order. The change will also raise the project cost because the alternative route will be longer than the original alignment, which was selected for its shorter length.

“That has to be settled first. After that, it has to go back to the Cabinet for approval. Only then will we issue the work order. By that time, the alternative alignment should be finalised,” Gowda said.

Also Read: Negotiate, re-estimate or re-tender: Options before CM DK Shivakumar on Adani tunnel road bid

‘Will contribute only ₹7,000 crore regardless of quote’

The decision to move the tunnel outside Lalbagh comes as the project faces mounting opposition and a steep increase in the contractor’s bid over the government’s original cost estimate.

Adani Enterprises emerged as the lowest bidder for two packages of the project, with a bid of ₹22,000 crore. This is more than 90 percent above the government’s estimated Total Concession Value (TCV) of ₹17,800 crore. Dilip Buildcon, Vishwa Samudra Engineering and Rail Vikas Nigam Limited (RVNL) were the other bidders.

The project’s initial estimate, under a Build-Own-Operate-Transfer (BOOT) model covering two packages, was approximately ₹14,000 crore. This comprised ₹8,000 crore for construction and ₹6,000 crore for maintenance. When the tenders were opened in December 2025, the estimate was revised to ₹17,800 crore, including return on investment, risk insurance, financing costs and other components.

“Changing to an alternative alignment will also increase the cost somewhat because the length will increase. Earlier, we had chosen the optimum length. Now, if we move away from that and the length increases, we will have to bear the additional cost accordingly. Until now, our expenditure was fixed. If there is any additional cost for this particular stretch, we will have to decide how to handle that. Otherwise, our contribution remains fixed, regardless of how much they quote.”

“We will contribute only ₹7,000 crore. They may quote ₹16,000 crore or ₹22,000 crore; it will not make any difference to our contribution. Whatever their estimate may be, the Government will contribute only ₹7,000 crore,” he said.

The government will have to decide how the additional cost arising from the change in alignment will be shared before construction can begin. The contractor will also need considerable time to mobilise resources and machinery.

(Edited by Dese Gowda)