No end in sight for Kerala seaport works deadlock as church-led protesters stay firm

Kerala's ambitious Vizhinjam Seaport has been facing deadlock due to the protest by the locals led by the Latin Catholic Archdiocese.

ByPTI

Published Nov 24, 2022 | 2:40 PMUpdatedNov 24, 2022 | 2:42 PM

Latin Catholic priests meeting with Shashi Tharoor to discuss issues related to Vizhinjam Port.(ShashiTaroor/Twitter)

By Rohit Thayyil 

The Kerala government’s ambitious ₹7,500-crore Vizhinjam Seaport, being developed by the Adani group in the southernmost part of the state, has been facing deadlock due to the over 100-day protest by the locals led by the leadership of the Latin Catholic Archdiocese.

Keen to finish the project as early as possible, the state government has appealed to the church authorities to end the protest as it was crucial for bringing changes to the industrial and economic sectors of the country.

The government claimed it has accepted almost all demands of the protesters. However, the protesters are not ready to budge, alleging the project will adversely affect the livelihood of the fishermen, the coastal ecosystem and the ecology of the Western Ghats due to the mining of granite stones for the same.

The agitators also alleged the government has not given any written assurances on their demands even after many minister-level discussions.

The Vizhinjam International Transhipment Deepwater Multipurpose Seaport is being developed in a landlord model with a Public Private Partnership component on a design, build, finance, operate and transfer (“DBFOT”) basis at an estimated cost of ₹7,525 crore.

Adani Vizhinjam Port Private Limited, the private partner, commenced the construction work on 5 December 2015. The port authorities clarified that 70 percent of the work has now been completed but for the last few months, the construction was halted due to the protests.

‘Construction affects coastal ecosystem’

The protesters have been demanding the construction of the deepwater port be stopped as it has affected the coastal ecosystem.

They have urged the government to conduct a proper environmental impact study of the project, besides putting forward six other demands including rehabilitation of families who lost their homes to sea erosion, steps to mitigate coastal erosion and financial assistance to fisherfolk on days weather warnings are issued.

Vizhinjam port. (Official Website/adaniports.com)

Vizhinjam port. (Official Website/adaniports.com)

The protesters have also urged the government to provide compensation to families of those who lose their lives in fishing accidents, subsidised kerosene for fishermen and a mechanism to dredge the Muthalapozhi fishing harbour in Anchuthengu in Thiruvananthapuram district.

Fr Eugene H Pereira, a church priest who represents the protesters, told PTI, the project is planned in a highly eroding coastal area which may adversely affect the fisherfolk. He said they have demanded an expert panel to study the impact.

Multiple ministerial-level meetings were held with the protesters to solve the crisis but the agitators claim that their demands were not met.

“The government has not yet given us any written assurances on anything. Our demand for kerosene has not yet been met. With regard to rehabilitation of displaced families and providing rent for their housing, the government needs to be proactive,” he said.

“The rent assistance is very less. The poor fishermen have to pay a huge deposit or advance for renting a house in a city area like this,” the priest said.

The state Fisheries and Port department authorities sought to pacify the protesting fishermen, saying the shoreline changes and other environmental aspects are being continuously monitored over a distance of 20 km on either side of the port.

‘Coastal erosion is being monitored’

Kerala Minister of Ports Ahammad Devarkovil said the National Institute of Ocean Technology and the National Centre for Earth Science Studies have been constantly studying the environmental parameters and the Shoreline Monitoring Cell appointed by the National Green Tribunal (NGT) has not yet made any observation regarding coastal erosion.

“The state government wants to finish the project as early as possible because it is a huge commercial activity which will bring major changes to the industrial and economic sector of not only Kerala but the country also,” Devarkovil told PTI.

Accepting the demands of the fishermen, the state government had on 6 October appointed a four-member expert panel to examine whether there has been any such coastal erosion consequent to the work done for constructing the Vizhinjam port.

The protesters complained the expert panel constituted by the government does not have any of their representatives.

Once completed, the world-class, future-ready port is the only transhipment hub in the Indian sub-continent, closest to the international shipping routes, and is centrally located on the Indian coastline.

Deadline may get extended: Adani Group

Meanwhile, the Adani Group, which has already moved the state High Court and secured a favourable order to continue the construction of the port, said if the protests continue, their deadline of December 2023 might get extended.

“We are losing a golden hour. The time period between September to May is best for undertaking work at sea as it will be comparatively calm. Now we have already lost three months. Our aim was to finish the project by December 2023. It might get extended due to this delay caused due to the protests,” a company spokesperson told PTI.

The company said almost 70 percent of the total work of the port has been completed but only 50 percent work of the berth construction and the breakwater work could be finished till now.

Of the 2,960 metre-long breakwater, around 1,400-metre work was finished using around 30 lakh tonnes of granite boulders.

“A total of 70 lakh tonnes of granite boulders are required to complete the breakwater construction. Earlier we were dumping around 15,000 tonnes of boulders per day but now we plan to increase it by 30,000 tonnes per day,” Port Department sources said.

‘Adani is cheating Kerala’

However, agitators claimed the Adani Group was cheating the Kerala government and the people of the state by giving false claims on work completion and environmental impact.

“The work has not reached 70 percent as claimed by Adani Group. They are cheating the Kerala government and the people of the state. They claim that they have purchased some cranes and other equipment. But those are still abroad. Now they need to mine the Western Ghats for the boulders for the rest of the construction. All these are going to adversely affect the environment,” Pereira said.

On 23 August, Kerala Chief Minister Pinarayi Vijayan told the Assembly that the protest seemed “orchestrated” and that the government was ready for talks, and wanted to resolve the concerns faced by the fishing community.

“We have accepted almost all of their demands,” a senior official from Minister Devarkovil’s office said.

“It’s not possible for the government to stop the project and conduct a study as it will invite huge compensation for delaying the project. The project was sanctioned after numerous studies as directed by the Supreme Court and the NGT. However, accepting their demand, the government has formed an expert panel,” the official said.

On reducing the price of kerosene, the official said it was decided by the union government and added “since bringing down the price was not an option, the state government has agreed to bear the cost of one-time conversion of such engines to diesel or CNG. We are already giving ₹25 as a subsidy on kerosene.”

The official said nowhere in India, fishermen are given compensation for the day when a weather forecast warning is issued.

A large number of people have been staging protests outside the main entrance of the multi-purpose seaport at nearby Mulloor for a few months.

Also read: Vizhinjam seaport makes CPI(M) and BJP strange bedfellows

Armed with the latest High Court order to continue with the construction works, the government said the construction-related vehicles will reach the port on Friday, 25 November.

The High Court has issued multiple stern warnings to the protesters asking them not to block the road or the construction. The court has also issued an order asking the Kerala police to provide security for the construction of the Port.